5 Why Analysis dan Implementasi Dies Multicavity dalam Peningkatan Produktivitas dan Efisiensi Tenaga Kerja pada Proses Pembuatan Lubang Pipa di Perusahaan Otomotif Indonesia
DOI:
https://doi.org/10.61722/jinu.v3i5.10930Keywords:
5 Why Analysis, Multicavity Dies, Bottleneck, Productivity, Labor Efficiency, Line BoringAbstract
Productivity is a primary indicator of manufacturing system success. In the type 3.2 pipe hole-making process at the line boring station of an Indonesian automotive company, a long drilling process problem was identified due to limited hole-making capacity and a bottleneck at the reaming stage, resulting in suboptimal finish good output. This study aims to identify the root causes using the 5 Why Analysis method and to analyze the effect of implementing multicavity dies on productivity and labor efficiency. A descriptive quantitative approach with a before-after comparison design was employed. Before data were collected over 63 effective working days (Juni-August 2025), and after data over 64 effective working days (September-November 2025). The 5 Why Analysis identified three root cause categories: machine (drilling produced only 1 cavity per stroke and generated burrs requiring reaming), safety (safety cover obstructed visibility and caused non-ergonomic work posture), and man (separated workflow required more operators). A 4-cavity multicavity dies was implemented, consolidating drilling and reaming into a single press dies operation. Results showed average finish good output increased from 3,869 to 5,204 pcs/day (+34.5%), while operators were reduced from 3 to 2 (33.3% labor efficiency). Multicavity dies effectively eliminated the bottleneck and enhanced overall system capacity
References
Antonius, D., Nanang, Y. S., & Ardana Wahyudi, F. (2025). Analisis Mengengurangi Downtime Pada Dies Dengan Menurunkan Problem Burry Dengan Menggunakan Metode QCC Dan FMEA (Vol. 7, Number 1). https://permadi.nusaputra.ac.id/index
Febianti, E., Lintang Trenggonowati, D., Sutanto, Y., Teknik Industri, J., & Sultan Ageng Tirtayasa Jln Jend Sudirman Km, U. (2020). Review Produktivitas Mesin Menggunakan Total Productive Maintenance (Studi Kasus Perusahaan Manufaktur). In Journal Industrial Servicess (Vol. 6, Number 1). http://jurnal.untirta.ac.id/index.php/jiss
Hasil Penelitian dan Karya Ilmiah, J., Rohmatil Maulidah, A., Utomo, Y., Buana Surabaya Jl Dukuh Menanggal XII, A., Menanggal, D., Gayungan, K., Surabaya, K., & Timur, J. (n.d.). Penerapan Metode Objective Matrix (OMAX) dalam Mengukur Produktivitas (Studi Kasus : Departemen Servis PT. Tri Mitra Lestari). In Jurnal Teknik Industri (Vol. 9, Number 2).
Ngudi Wiyatno, T., Putri Riandani, A., Fitra, A., Rahayu, S., & An Khofiyah, N. (n.d.). PENGENALAN KONSEP DASAR LEAN MANUFACTURING PADA PERUSAHAAN SME (Small Medium Enterprise). In Jurnal Pengabdian Kolaborasi dan Inovasi IPTEKS (Vol. 1).
Ongbali, S. O., Afolalu, S. A., Oyedepo, S. A., Aworinde, A. K., & Fajobi, M. A. (2021). A study on the factors causing bottleneck problems in the manufacturing industry using principal component analysis. Heliyon, 7(5). https://doi.org/10.1016/j.heliyon.2021.e07020
Sari, R. D. P., & Oktora, S. I. (2021). Determinan Produktivitas Tenaga Kerja Industri Manufaktur Besar dan Sedang di Pulau Jawa. Jurnal Ekonomi Dan Pembangunan Indonesia, 21(2), 185–203. https://doi.org/10.21002/jepi.2021.12
Shinta Devi, F., & Setiafindari, W. (2024). ANALISIS PRODUKTIVITAS MENGGUNAKAN METODE OBJECTIVE MATRIX DAN FAULT TREE ANALYSIS PADA PROSES PRODUKSI E-MOTOR PT ABC. JURNAL ILMIAH TEKNIK INDUSTRI DAN INOVASI, 2(1), 30–44. https://doi.org/10.59024/jisi.v2i1.589